SSEN Transmission optimises Outage Planning with N-SIDE

<strong>SSEN Transmission optimises Outage Planning with N-SIDE</strong>
Topics
Outage Planning
TSO
Page published on
February 24, 2026

Summary

In this case study, you will discover details regarding:

  1. The current outage planning challenges for SSEN Transmission.
  2. The innovative Year-Ahead Outage Optimiser developed by N-SIDE, which utilises multi-objective optimisation and automatic validation.
  3. The advantages of implementing the tool. Alongside the proof-of-concept results, SSEN Transmission’s published close-down report estimates potential lifetime cost savings of £5.7 million, with year-ahead outage planning response times reduced from one hour to ten minutes in the latest trials.
  4. Finally, the conclusions from the proof of concept.

Project Introduction

The project, funded through Ofgem’s Network Innovation Allowance (NIA), aims to introduce a data-driven approach to outage planning through strategic collaboration. For electricity transmission operators, outage planning is a complex puzzle of balancing network security, resource limits, and a high volume of work. Planners must constantly navigate these competing goals, often forcing difficult trade-offs between maximising work delivery and minimising network disruption. SSEN Transmission partnered with N-SIDE to develop a Year-Ahead Outage Optimiser tool to transform this manual process into a strategic advantage.

The image shows the "Year Ahead Outage Optimiser".

Outage Planning Validation: This feature automatically scans an outage plan to identify any “clashes” or violations of pre-defined operational rules.

Customer Challenge

The large-scale integration of renewable energy sources has exacerbated the volatility of SSEN Transmission’s outage planning. This intensifies the challenge of balancing competing goals, creating a complex, dynamic environment where planners must manually manage a high volume of changes. This results in a significant workload and slower, more reactive decision-making.

Testimonial

Stephen Munro
Stephen Munro
Innovation Development Engineer, SSEN Transmission
The Year Ahead Outage Optimiser tool, developed with our fantastic partners at N-SIDE, represents a clear leap forward in codifying the network knowledge and experience of specialised engineers. Working closely with the great team at N-SIDE, we have developed a tool that can support our engineers to manage outage plans more effectively, helping deliver our clean power 2030 ambitions.

The Solution/Approach

To measure its impact, the outage planning tool was applied directly to SSEN Transmission’s historical data in a three-step process:

  1. Automatic plan validation: First, the Outage Planning Validation module scans the existing benchmark plan. This module serves as a critical feasibility check for any schedule, automatically identifying “clashes” (violations of predefined operational and resource constraints) that are time-consuming to detect manually.
  2. Multi-objective optimisation: Next, the core Outage Planning Optimisation engine is fed with the entire list of work requests. It uses its multi-objective function to generate a new, fully compliant schedule that balances competing goals: maximising delivered requests, minimising outages, and ensuring network stability.
  3. Ad hoc change management: Finally, the Single Request Analysis feature demonstrates an automated workflow for managing ad hoc changes. This feature provides immediate decision support to planners, enabling them to find the optimal slot for a new request with minimal disruption.
The Image shows "Outage Planning Optimisation"

Outage Planning Optimisation: This is the core engine of Year-Ahead Outage Optimiser. It takes a list of requests with original planned dates and generates a new, fully compliant, and optimised schedule.

Implementation

Beyond the core algorithm, the solution was designed as ready-to-use software specifically tailored to SSEN Transmission’s needs. It features a centralised interface that boosts collaboration and simplifies the planning validation process. The tool is designed to support decision-making rather than replace it, keeping planning engineers firmly in the driver’s seat.

Benefits

The proof of concept confirmed that the outage planning tool provided a robust, flexible solution that achieved preliminary success in key areas:

Quantitative results (12-month benchmark)

orange checklist icon

The tool successfully scheduled 99.5% of all work requests

blue decreasing data graphic icon

Reduced the total number of outages by 34%

drawing of an high-voltage electricity pylon

Cut total outage-days by 7.5%, directly increasing network availability

Reported net benefit

SSEN Transmission’s published close-down report provides an additional view of the tool’s potential value in deployment. Its cost-benefit analysis estimates:

 

  • £5.7 million in lifetime cost savings, reducing base planning costs from £11.8 million to £6.1 million over a 45-year asset life.
  • A £268,000 scaled benefit until the end of RIIO-T3, reflecting the initial discounted savings window ahead of a potential full implementation.
  • A reduction in year-ahead planning response time from one hour to ten minutes in the latest trials. For current-year requests, which were not tested, the report estimates a potential time reduction of up to 50%.

    Strategic capabilities

    The Year Ahead Outage Optimiser tool provides a critical safety and compliance net by automatically identifying violations in the benchmark plan, ensuring a feasible baseline for operations. The Flexible Optimisation feature, driven by its multi-objective function, empowers planners to customise the definition of an optimal plan, allowing them to weigh “maximum delivery” against “maximum network uptime”. Furthermore, it enhances schedule stability by minimising work shifting and reducing customer impact by prioritising preferred periods.

    The tool also enables strategic decision-making through a powerful “What-if” Sensitivity Analysis feature, allowing planners to run scenarios by adjusting constraints and priorities before implementation. Finally, for day-to-day operations, the tool provides a clear path to reduce the time and effort required to manage ad hoc changes.

      The image shows: "Single Request Analysis"

      Single Request Analysis: This module instantly finds the optimal, least disruptive slot for a request and explains planning constraints.

      Conclusion

      The proof-of-concept successfully concluded in November 2025, with a definitive result: the tool eliminates the compromise TSOs faced, proving that high work delivery and operational efficiency can be achieved. The report confirms that the proof of concept demonstrated the core capabilities needed for plan validation, optimisation and single-request analysis. The full public report is available through the Energy Networks Association’s Smarter Networks Portal

      Author
      Sergio Z. Perilla
      Sergio Z. Perilla
      Senior Energy Analytics Consultant
      Sergio holds a double master’s degree from KTH (Sweden) and TU/e (The Netherlands) and brings over 5 years of experience to the energy sector. At N-SIDE, he bridges the gap between client needs and technical implementation, specializing in power matching algorithms, grid operations, and outage planning. His work leverages mathematical optimization and data science to solve complex challenges in power systems and electricity markets.
      Upcoming Webinar
      Register for N-SIDE's upcoming webinar with SSEN-Transmission!
      Visit our page
      Learn more about how N-SIDE's advanced analytics can optimise your grid operations.